• Report takes stock of the UK’s public charging network as UK progresses towards electrified transport and government target of at least 300,000 public chargers by 2030.
  • Zero Emission Vehicle (ZEV) mandate key to underpinning supply and supporting charger growth.
  • UK on track to hit 300,000 charger target despite fears over drop in installation.
  • Charging an EV is cheaper than filling up a petrol or diesel car when it is charged at a price lower than 0.687 £/kWh - meaning around 70% of all public chargers in the UK provide running cost savings to EV drivers.

FT - pa_gridserve Electric HIghway_03

A new report by New AutoMotive claims the UK is on track to meet the government’s target of 300,000 public chargers for electric cars by 2030.

However, findings of the report - ’On the Road to 2030’ - show that industry uncertainty over future demand for electric vehicles (EVs) was holding back growth in charger numbers.

But it pinpointed the government’s Zero Emission Vehicle (ZEV) mandate as a key guarantee of EV supply, meaning future demand could be matched and ensuring the charging network grows quickly.

Barriers to installing more charge points

A major barrier identified by the report is a lack of clarity around future demand among industry stakeholders. The report says the forthcoming ZEV mandate is the government’s most effective means of driving EV uptake by ensuring the supply of electric cars, providing industry with certainty around future demand, and thus ensuring that the UK’s public charging network continues to expand at pace.

Many of the barriers identified in the report have slowed charge-point installations in recent months. In some cases, the report found reasons for optimism that these would cease to be a problem in the future. Other barriers explored by the report include:

  • Regulatory changes: The report found that recent changes to regulation around installing and operating charge points had disrupted some charging infrastructure operators’ plans in the short term, but that this should cease to be a problem in 2023.
  • Electrical connection costs:  A key barrier to installing additional infrastructure identified by the report has been the cost of upgrading local electricity connections to accommodate higher usage. The report finds that a recent decision by Ofgem to reform charges for electrical grid connections should reduce a significant barrier to future new charge points being installed.
  • Land access and planning permission: Another barrier identified by the report is the difficulty in securing permission to lay new electrical cabling across land. The government recently consulted on reforming access rights to remove this barrier, and the report urges the government to proceed with this work in 2023.

UK charging rollout on track

The report has found that the UK’s infrastructure rollout is on course to meet key government targets. Based on current trends and available data, New AutoMotive project the public network will continue to grow in the lead up to 2030, delivering the government’s goal of 300,000 chargers.

Contrary to a recent AA report, New AutoMotive calculates that charging via the public network often offers significant running cost savings for electric car owners. Electric cars charged at 68.7p/kWh work out cheaper to run per mile than diesel and petrol cars, and around seven in 10 public chargers are below this price point. The average cost of charging via Podpoint (47p/kWh), Chargeplace Scotland (30p/kWh), Ubitricty (42p/kWh), and BP Pulse (52p/kWh), collectively the four largest public providers in the UK, all fall well below this figure, meaning they offer significant running cost savings to motorists.

Ciara Cook, research & policy officer at New AutoMotive, commented: “Before they make the switch to an electric car, motorists need the confidence that they will be able to charge their cars when and where they need to. There have been a lot of concerns recently about the UK’s electric car charging infrastructure. This report represents the most comprehensive examination thus far carried out on the UK’s fledgling charging infrastructure industry. The findings are reassuring, especially given recent concerns around the rate of network growth.”

“The network is not perfect - it is still a work in progress, and there are definitely still teething problems with both the existing infrastructure and the rollout of new infrastructure. However, the rollout is progressing at an adequate pace, growing by a third every 12 months, and the UK is on track to meet the government’s target of 300,000 public chargers by 2030.”

“The government can speed up the rate of the network’s growth by addressing the barriers identified in this report. The most crucial barrier the government can help industry overcome is uncertainty about future demand for public charging services. The forthcoming ZEV mandate is the most powerful tool at the government’s disposal as it seeks to overcome these barriers; it will ensure the supply of EVs in the UK meets demand, resulting in more electric cars on the road, and providing the charging infrastructure industry the security and certainty it requires to continue to grow at pace.”